Construction Status Report - Orange Ave
Click here to view photos of the Orange Ave Redevelopment.
January 3, 2023 Status Report
- Demolition contract complete.
- Temporary Power is "ON" at the site.
- All underground site work has been completed.
- Water taps completed. Service main installed. Lateral building branches being installed.
- Building 1 foundation ready for Concrete Pour. We are delayed on this due to a revision needing to be approved by CoT. We have completed the resubmission. Waiting on clearance to proceed. Pour set for 1/10/23 Tentatively.
- Foundation crews working on Building 2. Concrete pour set for 1/10/23.
- Building 3 Underground plumbing complete. Concrete pour set for 1/17/23.
- Building 4 Underground plumbing complete. Concrete pour set 1/24/23.
- Building 5 Pad did not pass material testing. Crews are working on recompacting and completing final lifts. Concrete pour set for 1/31/23.
- Electrician has started placing underground conduit at Bldg. 3/4.
- Mad Dog team plans to distribute all job applications received to subs in January.
- THA Team has narrowed naming down to 2 options. (The Gardens @ South City, The Gardens @ Orange Ave)
- Lumber is still being delivered and stored onsite