Orange Ave Redevelopment Project Progress - January 3

 Building 1 pad is being constructed.

Building 1

 Workers are working on building 2 pad.

Building 2

 Pipes are sticking out of the ground near building 3 pad.

Building 3

 Pipes are sticking out of the ground near building 4 pad.

Building 4

 The ground has been smoothed out where building 5 pad will eventually sit.

Building 5 pad

 New sidewalks are being poured along Orange Ave.