Orange Avenue Redevelopment - October 2022 Progress Photos

The future site of a Stormwater Detention Pond.

Stormwater Detention Pond- Phase 1.

Tall grass has grown up around one of the old buildings in phase 2.

Abatement of Phase 2.

Hardie siding is sitting outside, onsite on some grass.

Hardie Siding is stored onsite.

Tractor tires have left marks in the dirt of the cleared Phase 1 site.

Phase 1 site clear.

A large pipe is set into the ground.

Storm bypass structures set.

A tractor works on installing drainage pipes into the large holes in the ground.

Storm bypass pipe installation.

All the drywall and insulation has been removed from the walls in Phase 2.

Phase 2 abatement.

A tractor is tearing down a building in Phase 2.

Phase 2 building demolition.

A tractor works at removing an old building slab.

Building slab removal.

Large storm bypass drainage pipes are stacked up, waiting to be set.

Storm bypass pipes.